Active Power Priority vs. Reactive Power Priority

Tim Taylor Tim Taylor

This is the fourth of five articles in the series “Reactive Power in Utility-Scale Solar PV Applications.” Here’s the last article – “Inverter-Based Resources Reactive Power Capabilities” – in case you need to catch up.

In the earlier articles in this series, we’ve looked at the purpose of reactive power, power ratings of utility-scale solar inverters, and how real power, reactive power, and apparent power are interrelated.   

We ended article 3 by looking at the reactive power capability curve of an inverter as shown in Figure 1.  For this inverter, the maximum reactive power injection/absorption is 0.6 x Apparent Power Rating (Srated).  This inverter is also capable of “Q at Night”, which can inject/absorb reactive power at night when no real power is being produced.

In this article, we’re going to focus on the right side of Figure 1 which looks a bit like a side view of one of Dr. T.J. Eckleburg’s eyes. (Literary reference, for those who were paying attention in high school English.  Explanation at the end of this article).

Active Power Priority and Reactive Power Priority

Modern inverters can produce reactive power and real power independently of each other unless the inverter is operating at its kVA limit. The question we’re addressing is when the inverter is operating at its kVA limit (Srated in Figure 1), and then a need to increase kW or kVAr production arises. 

The need for increased real or reactive power production may be during steady-state conditions or during or following a system contingency.  The request could be a result of the inverter’s reactive power control, a control signal from a plant controller or the control center, or increased availability of the solar resource with a resulting increase in DC power to the inverter.

Let’s look at Figure 2 below.  Let’s assume our inverter is operating at kW1 and kVAr1.  This results in operation at the red square on the kVA rating curve. Now let’s assume that the transmission or distribution operator, or the inverter’s reactive power control algorithm, requests the inverter to produce more kVAR, to a level represented by kVAr2.  Since the inverter is already maxed to its kVA rating, there are two options. 

First option: if the inverter is operating in what’s called “Active Power Priority” mode, then active power (kW) takes precedence over kVAr.  That means that the inverter will continue to operate at kW1, and not increase the reactive power output from kVAr1 to kVAR2.   This is good for the owner of the facility, since it continues to produce at the same level of kWh.  This means maintaining revenue production, if our facility is selling power.  The tradeoff is that the kVAR level is not increased as requested, which may be to the detriment of power system operations.

Second option: if the inverter is operating in “Reactive Power Priority” mode, then reactive power (kVAr) requests take precedence over kW.  Since at the red square the inverter is already operating at its kVA rating, the only option to produce additional kVAr and reach kVAr2 is to reduce active power production to kW2.  The good thing is that the requested number of kVAr is now being produced.  The tradeoff is the revenue-producing kW has been reduced by an amount equal to kW1 – kW2.  

Keep in mind that this only happens when the inverter is already operating at or near its kVA rating.  In many cases with Solar PV facilities, this is usually quite a small amount of time.  However, it can be common for a Solar PV plant to reach peak production while the system requires more VArs.  In those cases, operation in reactive power priority mode can contribute to system stability during disturbances by providing reactive power to the system when it is most needed.

A similar situation can also arise if your inverter is operating at its kVA rating at unity power factor (0 kVAr) and the system operator asks you to adjust your inverter to operate at a non-unity power factor (say, 0.96).  You’ll have to give up some kW at peak time to be able to produce the required kVAr and reduce power factor to that value.

IEEE 1547-2018TM

IEEE 1547-2018, which more US states are adopting for distribution interconnection requirements, specifies that DER be capable of Reactive Power Priority.  At any operating point above 20% of rated active power, reactive power injection or absorption shall not constrain the delivery of reactive power up to certain limits. Further details can be found in Clause 5.2 of the standard. 

If you’re a solar PV developer or owner, it’s prudent to see if your system operator mandates “Reactive Power Priority” and size the inverters accordingly.  

(Answer to the literary reference mentioned earlier, if you haven’t Googled it yet: F. Scott Fitzgerald’s The Great Gatsby!)

Tim Taylor is the founder of Electric Distribution Academy, and all his courses are hosted exclusively on HeatSpring.  Tim is the instructor for several courses focused on utility distribution, including “Interconnection of Utility-Scale Solar PV to Distribution” and “Understanding IEEE 1547-2018 – Interconnection Standard for DER on Distribution.

Tim Taylor
Written by

Tim Taylor

Tim is an instructor of electric power distribution courses for HeatSpring and the owner of Electric Distribution Academy. He has been working with electric distribution systems for over 30 years, is a senior member of IEEE, and a member of the DISTRIBUTECH International Advisory Committee, with a focus on the Resiliency Planning and Preparation track.

More posts by Tim