Why Neutral and Ground Bond Only Once Brit Heller Neutral and ground get bonded together at the main service panel, and nowhere else. Leave the bonding screw in at a subpanel and everything still seems to work. The lights come on and the appliances run. So why does the code care so much? The answer comes down to parallel paths. A second bond puts everyday return current on ground wires and metal you can touch, which raises the shock risk if a neutral connection loosens, and can make ground fault devices nuisance trip. In this clip from HeatSpring’s Residential Wiring – Service Entrance Cables course, Journeyman Electrician and NABCEP PVIP Jenny Conrardy walks through what the single bond does, what goes wrong when a second one shows up downstream, and how to fix it at a subpanel. The full course follows power from the utility transformer to the main breaker, covering meter enclosures, service entrance conductor sizing, grounding electrodes, and the NEC requirements for mounting a service panel. Enroll in Residential Wiring – Service Entrance Cables! Transcript Neutral and ground join only at the service The main panel is the system’s one bond. Here’s why it has to be the only one. The equipment ground is meant to sit idle. It carries current only during a fault, just long enough to trip the breaker. So that’s for about a millisecond. Other than that, the ground sits with no current on it. It’s a non-current-carrying conductor. On the left, the system is bonded once at the main panel. Current from the subpanel’s loads comes back on the neutral alone, and the ground wire carries nothing. On the right, someone left the bonding screw in at the subpanel. Now neutral and ground are tied together at both ends, which makes them two parallel paths back to the main panel. Current divides between parallel paths, so part of the everyday neutral current now flows on the ground wire and on any metal conduit, panel enclosures, and appliance frames connected to it. That causes three problems. Current is on the ground path where it doesn’t belong. Metal you can touch is now carrying current, and if a neutral connection loosens, the shock risk gets worse. And protection misbehaves. Ground fault devices can nuisance trip, and the stray current causes heating and interference. The code calls this objectionable current and prohibits it. The fix at a subpanel: remove the bonding screw or strap, isolate the neutral bar, and land the grounds on a separate bonded ground bar. It’s separating the grounds and neutrals. Electrical Electrification Journeyman Exam Prep Licensed Apprenticeship Operations & Maintenance Safety Solar Solar miscellaneous Solar Utility Interconnection Originally posted on October 26, 2026 Written by Brit Heller Director of Program Management @ HeatSpring. Brit holds two NABCEP certifications - Photovoltaic Installation Professional (PVIP) and Photovoltaic Technical Sales (PVTS). When she isn’t immersed in training, Brit is a budding regenerative farmer just outside of Atlanta where she is developing a 17-acre farm rooted in permaculture principles. She can be found building soil health, cultivating edible & medicinal plants, caring for her animals or building functional art. More posts by Brit